| |
13
May 2008 Significant drill intercepts at North Lanut, Indonesia
In March 2002 Avocet purchased
an 80 per cent interest in an Indonesian company,
now named PT Avocet Bolaang Mongondow (PT ABM).
It holds a 6th generation Contract of Work (CoW)
located in the central portion of North Sulawesi
in the District of Bolaang Mongondow. The North
Lanut gold mine is located within the CoW, which
includes exploration and mining rights over approximately
50,000 hectares. An Indonesian company, PT Lebong
Tandai, owns the remaining 20 per cent.
Following a one year construction
period, gold production commenced in October 2004.
Exploration activities have continued within the
CoW with the Bakan project being the most significant
prospect that has arisen.
In May
2007 North Lanut passed five million man hours
with no lost time injuries (LTI), a significant
milestone for the operation. Unseasonal rainfall
at the North Lanut operation in early 2006 required
the mine to conduct some re-engineering of the
waste dumps and storm water ponds for the dump
leach. This work was undertaken during the first
half of the year. During the same period, heavy
rainfall hampered operations with the mine's haulage
fleet unable to operate at full capacity. Construction
of the second stage heap leach pad continued throughout
the period. These factors meant that the amount
of ore placed and irrigated on the leach pad in
the first half was 11 per cent below the corresponding
period in the previous year. This was partly compensated
by ore grades 8 per cent above the corresponding
period in the previous year, but recovery was
5 per cent lower. This was in line with expectations
as the mine is increasingly moving from oxide
to transitional/sulphide ore with depth. First
half gold production was therefore 9 per cent
down on the previous year. The greater focus on
waste last year means that stripping in the coming
year will be lower.
The mine made the decision to
hire articulated dump trucks for ore and waste
haulage, and a fleet of six contractor Volvo ADT
trucks started operation in the first quarter
of 2007. With larger and wider tyres, these trucks
are able to operate in very wet weather. This
helped place more ore on the leach pad in the
second half of the year which was some 35 per
cent higher than in the first half. This was still
18 per cent below the corresponding period in
the previous year, and although grades were 15
per cent higher than in the second half of the
previous year, recoveries were 9 per cent lower.
Leach recoveries reduced partly due to a higher
proportion of transitional ore leached in the
last quarter. Significantly higher levels of material
were placed on the pad in the final quarter, which
has benefited gold production in the first quarter
of the new year. For the year as a whole, gold
production of 48,170 ounces was 12 per cent below
the previous year. Total operating costs were
affected by the abolition of government funded
fuel subsidies, which significantly increased
diesel prices, while higher amounts of transitional
ore leached meant a significant increase in the
usage of hydrated lime which is used to control
the leach alkalinity. Combined with lower gold
production, these factors resulted in cash costs
for the year as a whole increasing from US$201/oz
last year to US$354/oz.
Decreasing recoveries and the
higher costs associated with transitional ore
mean that unit costs will continue to come under
pressure. The new haulage fleet will help by making
production more reliable in wet conditions. Drill
and blast will benefit from a new Tamrock Pantera
1100 blast hole drill received and commissioned
on site in May, and from the use of emulsion explosives
anticipated from August. In addition, the economic
benefits of crushing transitional ore are being
assessed, with significant recovery improvements
expected; engineering has progressed from conceptual
to detailed design, and much of the facility can
be used at Bakan when mining at North Lanut is
complete.
Importantly, and despite the
heavy rainfall experienced in the year, environmental
compliance was maintained throughout the year.
Rehabilitation has been ongoing, with trees being
planted around the new second stage leach pad
following its completion in February and around
the waste dump areas. Revegetation minimises erosion
in newly established dump areas. Sediment ponds
are being well maintained with regular cleaning,
which is an important control for sediment loadings
to maintain water discharge compliance.
|