Resources and Reserves Tables
Indonesia
Malaysia

  Focused on Gold Mining in South East Asia
 
Malaysia – Penjom

News

01 April 08 - Avocet upgrades resource at Penjom mine, Malaysia

Background

The Penjom Gold Mine is located in the State of Pahang in the centre of Peninsular Malaysia and is Malaysia's largest gold producer. Penjom commenced production in December 1996. The mine was developed by Avocet Gold Limited, a wholly owned subsidiary of Avocet Mining PLC, with the support of the Pahang State Development Corporation.

The Penjom deposit was developed from grass roots exploration by the Company in the early 1990s. The mine commenced production using conventional gravity and carbon-in-leach (CIL) process technology for the recovery of gold. However, these systems became ineffective as the ore mined at Penjom became increasingly carbonaceous and process recovery rates fell below 50 per cent two years after operations commenced. Penjom successfully solved this problem by developing unique processing systems which include complex gravity circuits and resin-in-leach (RIL) technology. Although this intellectual property has not been patented, the Company believes it has potential positive uses in other highly carbonaceous gold projects globally.

Operating results - FY2007

In April 2007 Penjom produced its one millionth ounce of gold, an important milestone for the mine, considering the project's original feasibility study indicated life of mine gold production of 223,000 ounces. Over the last five years, Penjom has successfully increased its resources and reserves on an annual basis. This trend is expected to continue.

The first half of the year was a challenging one due to high stripping and lower mined tonnes and grades than in the previous year. At the start of the year, the Kalampong East pit was near the end of its existing design life. The bottom of the pit was small and becoming congested with the high number of small contractor trucks operating within its narrow width. Prior to this, in November 2005, the Company announced a significant increase in Penjom's life of mine plan to over half a million ounces, which resulted in the design of a much larger pit to allow the additional ounces to be mined. Significant waste stripping was required especially in the first half of the year and this, together with congestion at the bottom of the pit, meant that ore mined in the first six months was less than half of the amount mined in the previous year. Over the same period, the grade of ore mined was also 30 per cent lower. Recoveries in the first half of the year were slightly ahead of the previous year. The second half saw a significant improvement in mined tonnes and grade, although lower mill grades continued to reflect the reduced grades mined earlier in the year.

During the second half of the year, Penjom successfully stepped up both mine and mill production in order to offset the impact of lower feed grades to the mill, and ore mined and milled exceeded the corresponding period in the previous year. Development was advanced to access ore below the east and west wall cutbacks. The grade of ore mined exceeded the previous year; however, high grade ore from the pit was highly carbonaceous and required blending with low grade material to control carbon levels through the mill. A key factor in the second half improvement was Penjom's decision to move to an owner operated haulage fleet. The contractor fleet, comprising 180 trucks of 13 tonne payload, was gradually reduced to 30 trucks on site at the year end, and replaced with 28 new Company owned Renault Kerax units, each with a nominal payload of 30 tonnes. The Kerax trucks are faster, more fuel efficient and lower in terms of unit costs per tonne moved in addition to which the reduced traffic congestion allows the mine to be more productive. Plant recovery in the second half was maintained at over 90 per cent despite lower head grades and a higher proportion of carbonaceous ore.

For the year as a whole, gold production of 95,966 ounces was 18 per cent below last year. Total tonnes mined at 18.1 million were 7 per cent below last year, and ore mined was 30 per cent lower, with mining taking place deeper in the pit. Mill throughput was in line with the previous year and recovery at 92 per cent was higher. However, mill feed grade averaged 5.67 g/t which was 20 per cent lower and accounted for the drop in production when compared with the previous year. Total operating costs were affected by increases in consumable prices, especially diesel, reagents and grinding media. Higher gold prices together with a full year since the Malaysian government increased royalty rates in January 2006 also meant that royalty payments were higher. Combined with lower gold production, these factors resulted in cash costs for the year increasing from US$242/oz last year to US$351/oz. Efforts to reduce unit costs resulted in an improving cost trend through the year and the average cost in the second half year was US$328/oz compared to US$370/oz in the first half. This reflects operating efficiencies in both mine and mill, notably the phasing out of the high cost contractor haulage fleet.

During 2007 Penjom will undertake a major expansion of its pit and associated infrastructure as part of its long term strategy to allow the economic exploitation of additional, but lower grade, reserves. An updated resource for Penjom was announced in October 2006, highlighting a 15 per cent increase in resources net of depletion. A review of options for an optimal pit design led to the further announcement in December of an increase of 132,900 ounces or 24 per cent to the life of mine forecast. The revised Proved and Probable Reserve at Penjom is 3.99 million tonnes grading 3.78 g/t Au (484,100 ounces of gold). The latest open pit design includes 0.84 million tonnes containing 135,600 ounces of gold (5.05 g/t Au average grade) of Inferred Resources, making a total life of mine forecast of 4.82 million tonnes grading 4.00 g/t Au containing 619,700 ounces of gold. The open pit reserve has expanded in the Manik-Janik area south of the main Kalampong pit, which will result in the merging of the Kalampong and Manik pits and therefore necessitate the diversion of the Jaleh Creek within the Penjom mining leases. Penjom is in the process of obtaining the necessary permits. There is room for the reserve to expand further, especially at depth and to the north of Kalampong. Nevertheless, the underlying resource requires further definition drilling. This work will commence shortly and form the basis of next year's resource and reserve expansion efforts. The new life of mine plan is lower grade than that reported last year, mainly reflecting additional low grades to the south. However, some stockpiling will allow the mine to prioritise the higher grade ore from the pit to the mill. Future mining will continue to select higher grades for processing, whilst retaining the low grade mineralisation for processing at a later date. Exploration, including deep drilling, continues at Penjom to the north, south and at depth of the main pit, where the orebody remains open, with a view to establishing extensions to the orebody and bringing further resources into the open pit mine plan or, alternatively, into a future underground mine development.

The resource at Penjom is now approximately one million ounces. As well as extending the mine life by over 100,000 ounces, the changes in pit design will improve annual production, by avoiding congestion and by making more mining areas available to allow consistent mill feed grade and tonnes. Production this year should be maintained at an annual rate of approximately 100,000 ounces per annum, despite anticipated lower grades, and cash costs will reduce owing to operating efficiencies. Work on the expansion is well under way and together with orders for capital items relating to the mining fleet and plant expansion, Penjom will spend approximately US$20 million in capital investment this year. The major items in the mine are 17 additional Kerax trucks, nine CAT 65 tonne excavators, two CAT 972 loaders, a CAT D10 dozer, two CAT D7 dozers and a Tamrock Pantera 1500 blast hole drill rig. An additional, larger mill required for the mill expansion has been purchased and is on site. Engineering for the tailings dam expansion is also complete. Foundation preparation commenced in July and buttress construction is expected to commence in August. The expansion of the pit means that the waste-to-ore stripping ratio over the next few years will exceed the life of mine ratio of 22.5 and the costs associated with this excess stripping will be deferred and released when the stripping ratio falls below 22.5. Production for the first half of this current year was 43,964 ounces at an estimated cash cost of US$320/oz compared to the corresponding period in the previous year of 50,759 ounces at US$370/oz.

Fact File
Operating company Avocet Gold Limited
Ownership 100%
Status Mining/Exploration
Product Gold
Mining method Open Pit
Plant Resin-in-Leach (RIL)
FY 2008 production 83,724 ounces
FY 2008 cash cost US$334/oz
General Manager Mohd Nazir Omar
Exploration Manager Peter Flindell