Focused on Gold Mining

Malaysia – Penjom

The Penjom gold mine is Malaysia’s largest gold producer and was developed by Avocet after applying modern technology to grass roots exploration in an area of historic alluvial mining.  The mine is located in Pahang State, approximately 120 km north of the country’s capital, Kuala Lumpur. The mine was commissioned in December 1996 with reserves of 223,000 ounces. Successful resource development means Penjom has produced over one million ounces of gold to date and still has over 1.2 million ounces of resource. In the late 1990s, Avocet was able to overcome initial problems of carbonaceous ore at Penjom by developing unique processing systems, including complex gravity circuits and resin-in-leach ('RIL') technology. These processes have potential applications at other carbonaceous orebodies. In 2008 Penjom expanded its mining and plant capacity with plant throughput increasing from 570,000 to over 700,000 tonnes per annum to compensate for decreasing mined grades.

Production at Penjom has been between 60,000 and 100,000 ounces per annum for the last three years. The table below shows the recent operating statistics at Penjom. The Penjom deposit is geologically and metallurgically complex and contains coarse gold that gives a significant nugget effect; such factors all result in a significant degree of variability in gold production, with periods when the mine has considerably exceeded planned gold production and periods when it has underperformed expectations. In order to facilitate more reliable short and medium term planning, a major drilling programme of over 80,000 metres has recently been completed. In March 2010, following this drilling the Company released an updated Mineral Resource estimate for Penjom that increased resources to over 1.2 million ounces (an increase of over 47%). The current mine life is approximately four years, but this will be reviewed once the updated resource model has been incorporated into the existing life of mine plan.

 

Register
If you require any further Investor information or would like to join our mailing list click here to email us your details.

Penjom – Operating statistics

 
Ore mined (tonnes)
Waste mined (tonnes)
Ore and waste mined (tonnes)
Ore processed (tonnes)
Average ore head grade (g/t)
Recovery rate
Gold produced (oz)
12 months eneded
31 Mar 2008__
561,000__
16,697,000__
17.258,000__
596,000__
4.84__
91%.
83,724__
31 Mar 2009__
699,000__
16,939,000__
17,638,000__
718,900__
3.47__
86%.
68,902__
31 Dec 2009__
972,332__
17,242,642__
18,214,974__
725,050__
3.24__
83%.
62,654__
Quarter ended
31 Mar 2010__
104,631__
3,735,151__
3,839,782__
185,378__
2.80__
83%.
13,669__
Cash costs (USD/oz)
- mining
- processing
- royalties and overheads
Total before deferred stripping
- deferred stripping
Total cash costs (USD/oz)
 
239__
97__
78__
414__
-__
334__
 
349__
167__
94__
610__
669__
528__
 
416__
181__
108__
705__
-__
705__
 
482__
218__
118__
818__
-__
818__


Malaysian resource and reserve summary

Below is an overview of the Company’s JORC-compliant Mineral Resources and Ore Reserves in Malaysia. The Mineral Resource figures quoted
are inclusive of Ore Reserves where stated. Mineral Resource and Ore Reserve figures for Penjom are as at 31 December 2009.

Penjom – Mineral Resources and Ore Reserves as at 31 December 2009

 
Ore Reserves
- Proven
- Probable
- Reserves subtotal
Gross
Tonnes__
 
1,398,000__
1,566,000__
2,964,000__
Grade (g/t)––
 
2.16__
4.00__
3.13__
Contained––
Ounces––
 
96,900__
201,600__
298,500__
Net attributable (100%)
Tonnes__
 
1,398,000__
1,566,000__
2,964,000__
Grade (g/t)––
 
2.16__
4.00__
3.13__
Contained––
Ounces––
 
96,900__
201,600__
298,500__
Mineral Resources
Measured
Indicated
Measured + Indicated
Inferred
Resources subtotal
 
-__
17,015,000__
17,015,000__
4,028,000__
21,043,000__
 
-__
1.83__
1.83__
1.52__
1.76__
 
-__
1001,100__
1001,100__
196,800__
1,197,900__
 
-__
17,015,000__
17,015,000__
4,028,000__
21,043,000__
 
-__
1.83__
1.83__
1.52__
1.76__
 
-__
1001,100__
1001,100__
196,800__
1,197,900__

(Mineral Resources are inclusive of Ore Reserves and excludes stockpiles. Penjom’s Mineral Resources and Ore Reserves are calculated at a cut-off grade of 0.5 g/t Au.